Encouraging Best Practice in Residential Aged Care Program: Final Evaluation Report
10.1 - Cost implications for government
prev pageprev page| TOC |next page
Based on data provided by each project the inputs for the program have been quantified, both in terms of expenditure and in terms of full-time equivalent staff. However, there are some key issues that need to be considered:
- Inputs for the program included a significant component for evaluation.
- The projects were relatively short-term in nature. In addition they started from a situation in which there was effectively no existing program. Therefore there were significant ‘establishment’ costs involved (e.g. recruiting staff, establishing relationships, developing materials, ensuring project staff themselves were well trained). Over a longer time frame the proportion of costs related to these initial ‘establishment costs’ would be significantly reduced.
- Governance costs are also likely to be significant for projects of this nature initially, but are likely to diminish over time.
Table 24 Estimated project expenditure by purpose of expenditure
Project No. | Expenditure by phase of project ($) | Total | |||
|---|---|---|---|---|---|
Governance | Establishment | Implementation | Evaluation | ||
1 | 193,558 | 33,060 | 726,573 | 107,485 | 1,060,676 |
2 | 90,865 | 62,000 | 271,310 | 357,890 | 782,065 |
3 | 153,240 | 33,275 | 808,045 | 107,220 | 1,101,780 |
4 | 1,300 | 31,000 | 1,139,940 | 123,000 | 1,295,240 |
5 | 166,588 | 48,671 | 195,554 | 96,647 | 507,460 |
6 | 130,785 | 41,816 | 427,299 | 64,979 | 664,879 |
7 | - | 20,000 | 435,341 | 260,784 | 716,125 |
8 | 97,500 | 13,500 | 507,253 | 137,100 | 755,353 |
9 | 95,288 | 125,165 | 381,464 | 271,563 | 873,480 |
10 | 173,239 | 115,065 | 879,583 | 210,363 | 1,378,250 |
11 | 242,991 | 45,094 | 288,670 | 104,764 | 681,520 |
12 | 248,173 | 27,847 | 475,707 | 138,146 | 889,873 |
13 | 29,856 | 111,636 | 846,353 | 166,155 | 1,154,000 |
| Total | 1,623,383 | 708,129 | 7,383,092 | 2,146,097 | 11,860,701 |
| % of total | 14% | 6% | 62% | 18% | 100% |
The data in Table 24 and Table 25 should be treated with some caution as the amounts are estimates only. For example, it is very difficult in some cases to separate out expenditure on implementation from expenditure on evaluation when a particular activity (e.g. baseline auditing) may have been used both for evaluation and implementation (by feeding the results back to facility staff to inform goal setting and action plans). What is notable is the very high cost of evaluation for three projects (31%, 36% and 46%) which skews the average amount of money devoted to evaluation (18%). The median cost was 15%.
Table 25 Percentage of project expenditure by purpose of expenditure
Project no. | Expenditure by phase of project ($) | Total | |||
|---|---|---|---|---|---|
Governance | Establishment | Implementation | Evaluation | ||
1 | 18% | 3% | 69% | 10% | 100% |
2 | 12% | 8% | 35% | 46% | 100% |
3 | 14% | 3% | 73% | 10% | 100% |
4 | 0% | 2% | 88% | 9% | 100% |
5 | 33% | 10% | 39% | 19% | 100% |
6 | 20% | 6% | 64% | 10% | 100% |
7 | 0% | 3% | 61% | 36% | 100% |
8. | 13% | 2% | 67% | 18% | 100% |
9. | 11% | 14% | 44% | 31% | 100% |
10 | 13% | 8% | 64% | 15% | 100% |
11 | 36% | 7% | 42% | 15% | 100% |
12 | 28% | 3% | 53% | 16% | 100% |
13 | 3% | 10% | 73% | 14% | 100% |
| Total | 14% | 6% | 62% | 18% | 100% |
Table 26 Implementation expenditure per facility
Expenditure item | Average cost |
|---|---|
| Salary expenditure on implementation per facility | $36,000 |
| Other implementation expenditure per facility | $23,000 |
| Total implementation expenditures per facility | $59,000 |
Table 27 Numbers of staff trained and training costs
Form of staff training | Total trained | Average salary cost per staff member trained |
|---|---|---|
| Staff trained through training workshops | 4,767 | $103 |
| Staff trained through academic detailing | 1,333 | $163 |
| Staff trained through other on-the-job training | 1,119 | $322 |
Another important cost in the program has been the cost of identifying, working with and supporting local facilitators (e.g. champions, link nurses) in the 10 projects which adopted this approach to change management. The 177 facility-based champions trained as part of the EBPRAC program cost an average of $2,197 in salaries and wages for project staff. No attempt has been made to allow for the different periods of time each week that these facilitators were employed in the role. As with all the other data that relies on estimates of how people have spent their time this cost is an estimate only.
Travel costs varied from a low of 2% to a high of 10% of total costs, averaging 7% across all projects, a total of approximately $640,000. Not surprisingly, the lead organisations with the lowest travel costs (2% and 3%) were located in Melbourne with all their participating facilities in close proximity.
Top of page

