Better health and ageing for all Australians

Encouraging Best Practice in Residential Aged Care Program: Final Evaluation Report

10.1 - Cost implications for government

Up to Publications

prev pageprev pageTOC |next page

Table of contents

Based on data provided by each project the inputs for the program have been quantified, both in terms of expenditure and in terms of full-time equivalent staff. However, there are some key issues that need to be considered:

  • Inputs for the program included a significant component for evaluation.
  • The projects were relatively short-term in nature. In addition they started from a situation in which there was effectively no existing program. Therefore there were significant ‘establishment’ costs involved (e.g. recruiting staff, establishing relationships, developing materials, ensuring project staff themselves were well trained). Over a longer time frame the proportion of costs related to these initial ‘establishment costs’ would be significantly reduced.
  • Governance costs are also likely to be significant for projects of this nature initially, but are likely to diminish over time.
Projects were asked to estimate costs across four phases, distinguished by the purpose of the expenditure – project governance, project establishment, project implementation and project evaluation. The results are summarised in Table 24. There are some, mostly minor, differences between the total amounts for each project in this table and the budget for each project in Table 1 at the beginning of this report.

Table 24 Estimated project expenditure by purpose of expenditure

Project No.
Expenditure by phase of project ($)

Total
Governance
Establishment
Implementation
Evaluation
1
193,558
33,060
726,573
107,485
1,060,676
2
90,865
62,000
271,310
357,890
782,065
3
153,240
33,275
808,045
107,220
1,101,780
4
1,300
31,000
1,139,940
123,000
1,295,240
5
166,588
48,671
195,554
96,647
507,460
6
130,785
41,816
427,299
64,979
664,879
7
-
20,000
435,341
260,784
716,125
8
97,500
13,500
507,253
137,100
755,353
9
95,288
125,165
381,464
271,563
873,480
10
173,239
115,065
879,583
210,363
1,378,250
11
242,991
45,094
288,670
104,764
681,520
12
248,173
27,847
475,707
138,146
889,873
13
29,856
111,636
846,353
166,155
1,154,000
Total
1,623,383
708,129
7,383,092
2,146,097
11,860,701
% of total
14%
6%
62%
18%
100%
To allow for the different amounts of money allocated to each project the same data is presented in Table 25 as percentages to give an indication of how each project allocated expenditure in proportion to the size of their budget.

The data in Table 24 and Table 25 should be treated with some caution as the amounts are estimates only. For example, it is very difficult in some cases to separate out expenditure on implementation from expenditure on evaluation when a particular activity (e.g. baseline auditing) may have been used both for evaluation and implementation (by feeding the results back to facility staff to inform goal setting and action plans). What is notable is the very high cost of evaluation for three projects (31%, 36% and 46%) which skews the average amount of money devoted to evaluation (18%). The median cost was 15%.

Table 25 Percentage of project expenditure by purpose of expenditure

Project no.
Expenditure by phase of project ($)

Total
Governance
Establishment
Implementation
Evaluation
1
18%
3%
69%
10%
100%
2
12%
8%
35%
46%
100%
3
14%
3%
73%
10%
100%
4
0%
2%
88%
9%
100%
5
33%
10%
39%
19%
100%
6
20%
6%
64%
10%
100%
7
0%
3%
61%
36%
100%
8.
13%
2%
67%
18%
100%
9.
11%
14%
44%
31%
100%
10
13%
8%
64%
15%
100%
11
36%
7%
42%
15%
100%
12
28%
3%
53%
16%
100%
13
3%
10%
73%
14%
100%
Total
14%
6%
62%
18%
100%
Table 26 summarises the expenditure, across all projects, of both salary expenditure and other expenditure devoted to implementation. For the purposes of data collection ‘other implementation expenditure’ consisted of three expenditure categories: payments to participating facilities, travel costs and other operating expenses. Implementation activities cost an average of $59,000 per participating facility across the whole program. This gives an indication of what a differently structured program might cost, one where governance and establishment costs were borne by facilities (which might be quite low depending on the nature of the project) and there was no evaluation.

Table 26 Implementation expenditure per facility

Expenditure item
Average cost
Salary expenditure on implementation per facility $36,000
Other implementation expenditure per facility $23,000
Total implementation expenditures per facility $59,000
Each lead organisation was asked to identify how much time was spent by each person employed on their project on the four project phases. The time spent on implementation activities was also estimated for each staff member (see Section 3.3.2 for details). The most time consuming aspect of implementation was the time spent establishing, organising and delivering the various education programs undertaken by each project which represented 12.9% of total project staff time. Details of the education and training are included in Section 5.1. The data were linked to data about project costs to arrive at a salary cost for training staff. Details of the number of staff trained and the salary cost of doing so are included in Table 27. On-the-job training was generally conducted 1:1.

Table 27 Numbers of staff trained and training costs

Form of staff training
Total trained
Average salary cost per staff member trained
Staff trained through training workshops4,767$103
Staff trained through academic detailing1,333$163
Staff trained through other on-the-job training1,119$322
The data in Table 27 provides an indication of the sort of trade off that needs to be made when deciding how education should be provided. As indicated elsewhere in this report the literature generally supports 1:1 and small group education as being more effective than larger ‘workshop’ style education (Forsetlund, Bjorndal et al. 2009) but this needs to balanced against the additional cost, as indicated in Table 27. It is difficult to judge whether the mixed outcomes achieved by the various education and training programs in the EBPRAC program (see Section 4.4) are consistent with the findings from the literature but there is a general sense that staff prefer more individualised, small group, education.

Another important cost in the program has been the cost of identifying, working with and supporting local facilitators (e.g. champions, link nurses) in the 10 projects which adopted this approach to change management. The 177 facility-based champions trained as part of the EBPRAC program cost an average of $2,197 in salaries and wages for project staff. No attempt has been made to allow for the different periods of time each week that these facilitators were employed in the role. As with all the other data that relies on estimates of how people have spent their time this cost is an estimate only.

Travel costs varied from a low of 2% to a high of 10% of total costs, averaging 7% across all projects, a total of approximately $640,000. Not surprisingly, the lead organisations with the lowest travel costs (2% and 3%) were located in Melbourne with all their participating facilities in close proximity.
Top of page

prev pageprev pageTOC |next page